Published on December 8, 2020 Updated on July 18, 2023

The Campus Condorcet Porte de la Chapelle building will be delivered by 2021/2022.

The Porte de La Chapelle site in 2016
The Porte de La Chapelle site in 2016 - © Vincent Bourdon

 

2025

New Academic Year

Estimated opening

2022-2025

AUTUMN 2022 - FIRST SEMESTER 2025 (ESTIMATED TIME-FRAME)

Campus construction

2022

2ND QUARTER

Invitation to tender for construction work

2020

FEBRUARY

Site handed back to the EPCC
 

FIRST QUARTER 2020 TO FIRST SEMESTER 2021

Injection work, basement shoring, monitoring surveying for injections
 

JUNE - JULY

Electronic public participation (EPP)
 

OCTOBER

Building permit granted

2019

SEPTEMBER 2019 - JANUARY 2020

Decontamination work

July

Land handed over by the City of Paris

2018

October

Submission of the final design

May

Approval of the preliminary design

2017

November

Start of conceptual design

October

Selection of Françoise Mauffray's architectural design

July

Signature of the ownership agreement between the State and the City of Paris

2016

July

Launch of architectural design competition

May

Approval of the overall functional programme

2015

November

Demolition work started by the City of Paris

June

Launch of project programming with the Attitudes Urbaines agency

2014

December

Acquisition of land by the City of Paris

 